ZeeZee’s Construction Company has the opportunity to select one of four projects (A, B, C, or D) or the null (Do Nothing) alternative. Each project requires a single initial investment and has an internal rate of return as shown in the first table below. The second table shows the incremental IRR(s) for pairwise comparisons between each project and all other projects with a smaller initial investment.

Investments and IRR(s)

Project Initial Investment IRR
Null $0 0.0%
A $600,000 44.0%
B $800,000 40.0%
C $470,000 39.2%
D $540,000 36.0%

Incremental IRR(s)

Increment Incremental IRR
B-A 28.3%
B-D 48.8%
B-C 41.4%
A-D 116.5%
A-C 61.0%
D-C 18.4%

If MARR = 20% then project _______(A, B, C, D, Null)is preferred based on an incremental IRR analysis.

If MARR = 30% then project________(A, B, C, D, Null)is preferred based on an incremental IRR analysis.

If MARR = 40% then project________(A, B, C, D, Null)is preferred based on an incremental IRR analysis.

If MARR = 50% then project ________(A, B, C, D, Null)is preferred based on an incremental IRR analysis.

Assume MARR = 30%. Which project is preferred based on an incremental ERR analysis? _______(A, B, C, D, Null, not enough information)

Solution:

15% off for this assignment.

Our Prices Start at $11.99. As Our First Client, Use Coupon Code GET15 to claim 15% Discount This Month!!

Why US?

100% Confidentiality

Information about customers is confidential and never disclosed to third parties.

Timely Delivery

No missed deadlines – 97% of assignments are completed in time.

Original Writing

We complete all papers from scratch. You can get a plagiarism report.

Money Back

If you are convinced that our writer has not followed your requirements, feel free to ask for a refund.

WeCreativez WhatsApp Support
Our customer support team is here to answer your questions. Ask us anything!